A fictional example
If an AI tool drafts a project plan, the project manager decides whether to accept it. The manager makes the same decision about a schedule, an effort estimate and the AI's list of risks. The manager also decides whether to send an AI-drafted change request to the client.
In Deloitte's 2026 Global Human Capital Trends survey, 60% of executives said they regularly use AI to support decisions. The survey covered more than 9,000 leaders in 89 countries, and the number of executives in it is not published. The figure is about the executives in that survey, not about project managers.
Below is one project decision made with an AI answer. The AI drafted the plan, and the project manager still had to check who could agree to it.
1. The situation
Gopal Krishnan is a project manager at an office fit-out contractor. Its head office is in Singapore. His team is fitting out a new office floor for a client. Handover to the client is due on 28 March. The ceiling works are 2 weeks late. Joinery means built-in wood fittings, such as cabinets and wall panels. Gopal needs a recovery plan this week.
2. What the AI produced
WhipbirdAI drafts a recovery plan from the crew plan and the supplier's dates. Its answer:
"Handover on 28 March holds if the joinery goes in before the final electrical test, not after. The crew plan and the joinery supplier's delivery dates allow it. I am 87 percent sure."
Illustrative dates and figures.
3. The check
Gopal does not send the plan to his crew yet. First he opens the contract programme, the dated work plan that the client approved at the start. In the agreed order of works, the electrical test comes before the joinery.
The new sequence may work on site. But it changes an order of works that the client agreed. That change is the client's decision, not the project manager's. The AI's answer did not say who had to agree, so Gopal had to find out.
4. The decision, and who was told
Gopal sends the AI's sequence to the client's project lead as a change request. He writes the reason beside it: the new order keeps the handover date. He also writes the risk. The joinery would cover 2 walls before the electrician had tested them.
The client's project lead agrees to the change on a condition. Before the joinery goes in, the electrician must test the 2 walls that the joinery will cover. Gopal then tells his site supervisor, the electrician and the joinery supplier about the new order.
5. What happened after
Gopal's team handed the floor over to the client on 28 March.
3 months later, the firm added one line to its recovery plans. Every plan now carries this line: "A change to the agreed order of works goes to the client before it goes to the crew."
A delivery team can rehearse a decision like this one before a real project depends on it. StepSim runs this kind of practice as a business simulation: people decide with an AI assistant, then a trainer leads the debrief.